NHPC commissions three of the four units of the Parbati-II hydroelectric project

2025-04-02 Infrastructure NHPC commissions three of the four units of the Parbati-II hydroelectric project NHPC commissioned three of the four units of the 800 MW Parbati Hydroelectric Project Stage II in Kullu district, The Tribune reported. The run-of-the-river scheme on the Parbati includes a 31.56-km head race tunnel. According to the report, the project was approved in 2002 at Rs 3,919.59 crore and began partial operation in September 2018. https://www.tribuneindia.com/news/himachal/nhpc-commissions-three-units-of-parbati-hydel-project India Himachal Pradesh Kullu Western Himalayas Parvati Valley NHPC